RT Delivers 6 Infrastructure Rehabilitation Projects Worth a Total of 104.97 Million Baht
RT has successfully completed 6 infrastructure rehabilitation projects for highways, totaling 104.97 million baht. The company continues to take on short-term projects for quick revenue recognition while actively bidding for new government and private sector contracts, focusing on cost control and risk management to enhance long-term competitive capability.
Mr. Chawalit Tanomthin, CEO of Right Tunneling Public Company Limited (RT), a specialist in tunnel excavation, civil engineering, and comprehensive geotechnical engineering, revealed that the company has completed the construction of 6 infrastructure rehabilitation projects for highways on schedule.
The projects include the rehabilitation of infrastructure damaged by flooding and disasters on Highway No. 1095, section controlled 0202, from Maena to Tha Khrai, between km 114+730 and km 123+780 (in segments), with a contract value of 34,886,436.93 baht in the Mae Hong Son Highway District.

The rehabilitation of infrastructure damaged by flooding and disasters on Highway No. 108, section controlled 0203, from Nong Haeng to Mae Surin, between km 265+880 and km 265+970 LT, has a contract value of 11,693,087.73 baht in the Mae Hong Son Highway District.
The rehabilitation of infrastructure damaged by flooding and disasters on Highway No. 108, section controlled 0201, from Mae Rid Bridge to Huai Ngo, between km 191+000 and km 191+180 RT, has a contract value of 16,691,774.99 baht in the Mae Hong Son Highway District.
The rehabilitation of Highway No. 2196, section from Nang Wa to Thung Samo, section 2, between km 31+860 and km 32+000 LT, has a contract value of 14,995,000 baht, and the repair and prevention of erosion on Highway No. 1252, section controlled 0100, from Pang Fan to Mae Ton Luang, section 5, between km 19+200 and km 19+290 RT, has a contract value of 14,918,699.63 baht.

Additionally, in June, RT delivered the rehabilitation of infrastructure damaged by flooding and disasters on Highway No. 1150, section from Khun Jae to Wiang Pa Pao, section 3, between km 72+425 and km 72+625, with a contract value of 11,787,120 baht, resulting in a total value of short-term projects delivered this year amounting to 104.97 million baht.
“The company remains focused on taking on repair and rehabilitation work for infrastructure affected by disasters, which is urgent and has a short execution time, allowing for quick revenue recognition. At the same time, we participate in bidding for large-scale projects from both the government and private sectors to ensure stable and continuous income, while efficiently managing projects within the specified time and budget, emphasizing cost control, risk management, and developing standard construction machinery and equipment to enhance long-term competitive capability,” Mr. Chawalit stated.